VDT links Plant Vogtle nuke cost overruns to Kemper Coal

Even the VDT has caught on to cost overruns for Kemper Coal and the new nukes at Plant Vogtle.

VDT posted an AP article 29 July 2013, Miss. deal may figure into Georgia nuclear plant, and Charlotte Observer posted it the day before, including Ray Henry as the author,

In Mississippi, the Southern Co. utility took financial losses when the cost of building a new power plant went over budget. In Georgia, another of the company’s projects is going over budget, but it has not yet taken a financial hit.

Southern Company subsidiary Mississippi Power promised utility regulators that it would charge its customers only for $2.4 billion in costs for building a coal-fired power plant in Kemper Country. Those customers will also have to pay off another $1 billion in bonds for the project, though the utility cannot make a profit off that borrowed money.

The utility’s deal in Mississippi has become a point of debate as Georgia regulators consider who should pay for the increased cost of building two more nuclear reactors at Plant Vogtle (VOH’-gohl), southeast of Augusta. Public Service Commissioner Tim Echols said he wants Southern Co. subsidiary Georgia Power to consider a Mississippi-style deal here, and Georgia regulators are carefully tracking financial developments in Mississippi.

Echols said he was interested in the idea of a project spending cap.

“I’m sure when they made that deal they didn’t think they were going to over the cap, but they did,” Echols said.

Oh, come now, they went 26 times over budget last time. Why would anyone believe Continue reading

Planning Commission on subdivision next to Moody AFB, REZ-2013-08 MFH Tract A @ GLPC 2013-07-29

Now you can see what they were looking at: those documents are on the LAKE website for REZ-2013-08 MFH, for a subdivision on Roberts Road immediately next to Moody AFB.

First County Planner Jason Davenport said a few words about the TRC recommendation.

Commissioner Ted Raker (Hahira) wanted clarification about this application would require additional changes to meet the requirements of the Unified Land Development Code (ULDC), specifically that it would not help with safety, fire, health, general welfare, etc. “In fact seven out of the eleven were negative.”

Davenport confirmed that that was correct, and that was staff’s analysis. Staff paid by your tax dollars, so you shouldn’t have to file an open records request and pay ten dollars when staff could just put it on the web with the GLPC agenda, which they also don’t now but could easily put on the web.

Nobody spoke for the request. Numerous people spoke in opposition.

Tom Kurrie said in 38 years of practicing law Continue reading

Documents for REZ-2013-08 MFH Tract A on Roberts Road

What the TRC recommended, who the TRC is, the parcel numbers, the Planning Commission board packet, and other related documents are on the LAKE web server for REZ-2013-08 MFH Tract A, 0181 025B & 0181 027, Roberts Rd, 123.45 ac., MAZ I to Residential PD, 184 lots, County Utilities, the rezoning next to Moody AFB that has been withdrawn. The parcel numbers above were not in the GLPC agenda but are in the recommendations of the Technical Review Committee (TRC).

Lowndes County Planner Jason Davenport to TRC 23 July 103, July 29th GLPC Lowndes County Rezoning Update,

Good afternoon Planning Commissioners.

Based on the TRC meeting this morning please find this month’s TRC rezoning recommendations and current analysis below or attached to this e-mail. Continue reading

Proposed development next to Moody AFB has been withdrawn (REZ-2013-08)

Received in response to an open records request to Lowndes County, here is the developer’s withdrawal letter, and correspondence between Lowndes County Zoning and Planning with Moody AFB confirming that this was indeed REZ-2013-08 MFH Tract A on Roberts Road that was withdrawn. It seems the U.S. Air Force would also like to see GLPC minutes online; that request came from Deputy, Housing Division, Air Force Civil Engineering Center, located in San Antonio, Texas.. Also, doesn’t Georgia open meetings law require a summary of actions taken within a few days of a Planning Commission meeting? -jsq

Date: Mon, 29 Jul 2013 19:56:40 -0400
Subject: MAZ-1
From: Roger Sevigny <rsevigny@alleneng.net>
To: Jason Davenport <jdavenport@lowndescounty.com>, <bslaughter@lowndescounty.com>
Cc: Mike Fletcher <mfletcher@lowndescounty.com>, Joe Pritchard <JPritchard@lowndescounty.com>

Gentlemen,

I had no idea of the county anger with MFH LLC. I thought Continue reading

Palisades nuke down 11 times since 2011

Decrepit nuke leaked radioactive water into Lake Michigan in May 2013, and “The same tank sprang a leak in 2012.” That reactor has been down so many times the reporter couldn’t count them all. When will we realize what Korea and now Japan has: the nuclear industry colludes to hide its mistakes from the public, and the public needs to do something about it.

David N. Goodman wrote for AP 6 May 2013, Nuclear Regulatory Commission: ‘Very slightly radioactive water’ enters Lake Michigan,

Early Sunday morning, the tank was ruled inoperable and the nuclear power plant began powering down. This is reportedly the ninth time that the facility has been shut down since 2011.

Nope, ten times; count ’em:

> Palisades nuke down 11 times since 2011

And it stayed down from May 6th to June 17th 2013. Plus who knows what it’s leaking now that they didn’t bother to take it down for? Continue reading

Path of proposed pipeline through Lowndes County

That pipeline that starts in PCB-polluted Anniston, Alabama, where would it cross Lowndes County?

Two routes, one north to south, another from Brooks County southeast to the Florida line.

Pipeline points with streets Pipeline points with imagery

On this google map, A is the land mentioned in Massive pipeline project may cross Lowndes, by Jason Schaeffer, VDT, 30 June 2013, B, C, and D several of the parcels listed in the letters Sabal Trail Transmission LLC sent Lowndes County (another is very near D). They all form pretty much a straight line north to south. The actual route probably Continue reading

The Korean nuclear mafia: power companies, vendors, and testers

Document-forging Doosan was just the tip of the Korean nuclear corruption iceberg.

It’s different stateside, right? San Onofre 2 and 3 Oh, wait: U.S. NRC is refusing to supply Congress with safety documents related to the closing of San Onofre. But Plant Vogtle is much safer, right? Southern Company CEO Tom Fanning told us so. Of course, he also told us Kemper Coal would come in on budget, and now SO is writing off $611 million after taxes. But that bad concrete pour, the misplaced reactor vessel, the leaking tritium; those are all flukes, right? Meanwhile, solar panels don’t leak tritium, and if you misplace one, you only lose money, not risk lives.

By Choe Sang-Hun in NY Times yesterday, Scandal in South Korea Over Nuclear Revelations,

Korean nuclear reactor Weeks of revelations about the close ties between South Korea’s nuclear power companies, their suppliers and testing companies have led the prime minister to liken the industry to a mafia.

The scandal started after an anonymous tip in April prompted an official investigation. Prosecutors have indicted some officials at a testing company on charges of faking safety tests on parts for the plants. Some officials at the state-financed company that designs nuclear power plants were also indicted on charges of taking bribes from testing company officials in return for accepting those substandard parts.

Worse yet, Continue reading

VDT wins awards, two for people who don’t work there anymore

VDT fourth in class in newspaper AP Georgia awards, half for people who don’t work there anymore.

VDT today, Times wins AP awards; I’ve added some links and notes in [square brackets]:

The Valdosta Daily Times won several awards at the recent Georgia Associated Press Managing Editors Newspaper Awards luncheon in Atlanta.

Former Times’ reporter Jason Schaefer received a First Place in Deadline Reporting award for his story on homeless individuals in 2012. [“Life on Hard Ground”, which apparently is not online, but apparently was published on paper 3 December 2012.]

Former news photographer Paul Leavy won a Third Place Award in Photography for his photo of a meth lab arrest at a local motel. [For Tip leads to meth lab raid 27 January 2012, by another former reporter, David Rodock.]

This is the first admission I’ve seen that Jason Schaefer doesn’t work there anymore, even though his byline hasn’t appeared since his last story on homeless people, 3 July 2013.

Kay Harris also won two awards, for Continue reading

Potential defects shipped to Farley reactors and four others

No worries about this reactor coolant system defect; Westinghouse says so, and didn’t even list Vogtle or Diablo Canyon, where Southern Company and PG&E said they were going to install these shields. Nevermind a reactor operator warned us back in January. Westinghouse did list “Beaver Valley Unit 2, Callaway, D.C. Cook Unit 1, Farley Units 1 and 2, and Wolf Creek”.

NRC Event Notification Report for July 29, 2013 Event Number 49217:

POTENTIAL EXISTENCE OF DEFECTS IN SHIELD PASSIVE THERMAL SHUTDOWN SEAL SYSTEM

“The defect being reported concerns an identified inconsistency between the intended design functionality of the SHIELD passive thermal shutdown seal (SDS) and that observed during post-service testing.

“The purpose of the SDS is to reduce current reactor coolant system inventory losses to very small leakage rates for a plant that results in the loss of all reactor coolant pump (RCP) seal cooling. The SDS is a Continue reading

Callaway nuke down since Friday near Kansas City, MO

Where there was black smoke in the turbine building there was fire that shut down a nuclear plant Friday. It’s still down today, with no estimate on uptime. This is after Callaway was shut down most of April and May due to an electrical fault that “injured or affected” four people. It’s only been up most of 4 months out of the past 6. Not so reliable, this baseload nuclear, is it?

Callaway down 2 out of 6 months

Margaret Gillerman wrote for the St. Louis Post-Dispatch 27 July 2013, Callaway nuclear plant shut down after a small fire,

FULTON, MO. • Callaway County’s nuclear plant has been shut down since shortly before midnight Friday when a small fire broke out in the turbine building, authorities said.

No one was injured.

“No personnel were hurt, and no radioactivity was released” above normal operating limits, Barry Cox, senior director of nuclear operations at Callaway, said Saturday. Cox said the fire was in Continue reading