Tag Archives: passenger rail

WSJ misunderstands why T-SPLOST was defeated

Inaccurate labelling is the reason T-SPLOST was defeated, along with Atlanta is not all of Georgia, but the Wall Street Journal doesn’t understand that.

Cameron McWhirter wrote for the Wall Street Journal 1 August 2012, Tea Party Ties Up Tax to Ease Atlanta Traffic

ATLANTA—Money and heavyweight endorsements don’t secure an election — especially when you propose higher taxes in a deeply conservative state with a robust tea-party movement.

A plan for a transportation sales tax was endorsed by Georgia’s Republican governor and the Democratic mayor of the state’s largest city. It was backed by the Metro Atlanta Chamber of Commerce and the area’s top businesses. It was pushed by top political consultants funded by more than $8 million in corporate and other donations.

Those against the plan were a loose coalition of tea-party activists, some environmentalists and a local branch of the NAACP. Their total raised? About $15,000.

But David slew Goliath.

That’s lazy reporting. Those “some environmentalists” included the Georgia Sierra Club, an organization which reportedly has more members than the state Democratic Party. And that’s just in Atlanta.

Opponents in our region included Democrat Ashley Paulk, who was on the T-SPLOST executive committee and is the current Chairman of the Lowndes County Commission, Democrat Gretchen Quarterman, who is the Chairman of the Lowndes County Democratic Party (LCDP) and is running for Chairman of the Lowndes County Commission, as well as Nolen Cox, Chairman of the Lowndes County Republican Party (LCRP), and Roy Taylor, LRCP First Vice Chair and well-known Tea Party activist, along with a wide range of other opponents.

Look at the difference between that Region 11 T-SPLOST vote map and this map of the Atlanta Metro T-SPLOST vote. Atlanta metro is clearly centered around Atlanta. Region 11 isn’t an economic region: the vote was split right down the middle between No on the east and west and Yes in between.

Region 11 throws together three population centers: Lowndes, Tift, and Ware Counties, with their largest cities Valdosta, Tifton, and Waycross. Lowndes and Tift are at least connected by I-75, and they and most of the ones around them voted against (Ben Hill, Turner, Berrien, Cook, Lanier, Echols, and Brooks). Ware County and all the counties east of it (Pierce, Brantley, and Charlton) voted against. In between there’s a complete barrier of counties that voted for T-SPLOST (Irwin, Coffee, Bacon, Atkinson, and Clinch). Those No counties completely separate the eastern Ware County group from the western Lowndes-Tift group.

The perception around here is that T-SPLOST was made up to affect metro Atlanta, and the rest of the regions were Continue reading

Why did old US 41 N increase from $8 M to $12 M? —John S. Quarterman @ SGRC 2011-09-19

I asked why the Old US 41 North widening project changed from $8 million on the unconstrained list to $12 million on the constrained list, an increase of $4 million or 50% when the description did not change? The answer indicates GDOT and local governments want to drive development north in the county, leaving pedestrians and bicyclists stranded yet having to pay.

Corey Hull responded:

Halfway through we received new cost estimates….

GDOT did the cost estimates, in cooperation with the local government that was responsible for that.

A state employee told me after the meeting that GDOT raised some estimates because it thought the local government, in this case the Lowndes County Commission and staff, didn’t put in enough to cover the project. I don’t know whether GDOT was figuring by Atlanta costs or not…. At least the cost didn’t go up further in the final project list; I just checked and it’s still $12 million.

Corey elaborated that some projects increased and some decreased. I asked him which ones did which. He said he’d have to go back and compare. Later he helped me produce a list of comparisons of costs of Lowndes County projects, which shows that one went down by 30% and three went up by 50% or more. One, RC11-000099 St. Augustine at Norman Intersection Improvements, went up by 131.5%.

That $12 million for widening less than 3 miles of one road is more than one item that was in the unconstrained list but cut from the constrained list: $7.5 million for a bus system, with three bus lines that would connect Wiregrass Tech, Five Points, Downtown, Moody, East Side, South Side, West Side, and the Mall. A bus system recommended by the Industrial Authority’s Community Assessment to aid in employee attendance, industry recruitment, and workforce.

You could probably even start up a substantial commuter rail system using existing freight line tracks for less than $12 million. Even though GDOT apparently only believes in roads and bridges, busses and trains are actually more cost-effective, especially for lower-income people. The same lower-income people who will be disproportionately taxed by T-SPLOST as a percentage of their income.

Instead, the description for the Old US 41 North project admits the county is driving Continue reading