Tag Archives: WWTP

Flood control measures encourage settling too close and provoke severe flooding events

Flood control to keep water out of houses seems like a good idea, but it turns out that it causes the flood control measures to keep needing to be raised higher, and it encourages people to build too close to flooding areas, plus “rare and catastrophic events take place”. Like the 2009 “700 year flood” and the four or more floods this year that have overflowed the Withlacoochee Wastewater Treatment Plant. In our case, there are also the issues of widespread clearcutting and buildings and streets with impervious cover. The local runoff containment requirements in the various local government zoning codes may be like levees: “flood control structures might even increase flood risk as protection from frequent flooding reduces perceptions of risk”.

This encourages human settlements in floodplain areas, which are then vulnerable to high-consequence and low-probability events.
Much simpler just not to give out building permits for flood zones. Or we could put medical buildings right next to a creek, assuming because it’s never flooded it never will….

Socio-hydrology: conceptualising human-flood interactions, G. Di Baldassarre, A. Viglione, G. Carr, L. Kuil, J. L. Salinas, and G. Bloschl, Hydrol. Earth Syst. Sci., 17, 3295–3303, 2013 doi:10.5194/hess-17-3295-2013, © Author(s) 2013. CC Attribution 3.0 License.

Abstract. Over history, humankind has tended to settle near streams Continue reading

Fourth or fifth flooding at Valdosta’s Withlacoochee Wastewater plant this year?

So many I’ve lost track; somebody help me….

Valdosta City PR Friday, Public Notice for Permit Violation at WWTP,

Due to continued heavy rains in Valdosta and surrounding areas in recent days, moderate flooding of the Little and Withlacoochee Rivers caused a hydraulic overload at the Withlacoochee Wastewater Treatment Plant. As a result of a peak hourly flow of 15.58 million gallons, the incident led to a discharge of total suspended solids in excess of the National Pollutant Discharge Elimination System (NPDES) permit limit.

The total suspended solids result for the effluent sample collected August 22, 2013 was 203 milligrams per liter. This is greater than Continue reading

Valdosta Utilities Department 5-Year Action Plan

Received 26 April 2013. Basically Valdosta is accelerating its plans to do something about wastewater, including adding pumpstations and force mains, as well as relocating the Withlacoochee Wastewater Treatment Plant uphill. Here are the summary pages; there’s much more detail in the plan. -jsq

Utilities Department 5-Year Action Plan:

Since 1992, the City has received $179 million in SPLOST funding and over the same time period has invested nearly $168 million in capital projects for the Water and Wastewater system. This includes SPLOST funding, system revenues, bonds, and GEFA loans.

Since 2009, the Utilities Department has expended over $49 million on sewer system improvement with approximately $5.6 million spent on the Withlacoochee Treatment Plant. When the projects listed below are completed by December 2018, the City will have invested approximately $230 million in capital projects for its Utilities system from 1992 to 2018, a 26-year period.

PUMP STATION, FORCE MAIN, HEADWORKS AND EQUALIZATION BASIN PROJECT

Continue reading