Tag Archives: Bobby Baker

Sun dancing as a Georgia Trend

GSEA, GaSU, Georgia Power, and even me are quoted in a Georgia Trend feature about solar power in Georgia. As Mahatma Gandhi is alleged to have said when asked his opinion of western civilization: “that would be a good idea!”

Jerry Grillo wrote for Georgia Trend July 2013, Sun Dancing: As Georgia’s solar capacity shoots skyward, a new state utility is proposed,

It’s the sun, the sol of our solar system, to which everything that lives and moves, including the wind, owes its existence. Without the sun, there is no us, no Earth. You can’t miss it. It’s the biggest thing in the sky, the biggest thing for at least 24 trillion miles, and at 4.5 billion years old it is middle-aged and remains the most abundant source of power between here and Alpha Centauri, zapping our planet every minute with more energy than humanity can consume in a year.

The best thing is, the sun is free. Still, for most of those eons, capturing the sun’s energy for human consumption has been like picking crops with a catcher’s mitt.

But over the past few years, photovoltaic technology (“photo” for light, “voltaic” meaning electricity) has gotten way more efficient, and the previously prohibitive price has fallen dramatically, setting the stage for what’s happening now in Georgia: Solar deployment and interest are increasing dramatically.

“This is a very dynamic time for solar energy, and it demonstrates a pent-up demand and interest in solar energy for Georgia,” says Mark Bell, chair of the Georgia Solar Energy Association (GSEA) and president of Atlanta-based Empower Energy Tech-nology. “There’s a great potential here for real, sustainable economic development.”

Grillo was pretty thorough in getting a range of points of view (with the notable exception of Georgia Sierra Club), and the whole article is well worth reading.

Among the things I told Grillo back at the beginning of May, I’m especially glad he included this:

Continue reading

15 month delay for new Plant Vogtle nukes —state inspector at PSC

Southern Company's new nukes are delayed at least fifteen months, at least a billion over budget and rising, and not organized to meet safety filing requirements, yet the Georgia PSC yesterday let SO pass the buck to contractors and Georgia Power continue charging customers for that boondoggle, despite 40 to 1 opposition from attendees.

Ellen Reinhardt wrote for GPB News yesterday, Plant Vogtle Construction Costs Rising,

An independent auditor told utility regulators Plant Vogtle construction will be delayed at least 15 months and go millions of dollars over budget.

Nuclear engineer William Jacobs said poor construction material, contractor mistakes and oversight delays will mean the Unit 3 reactor won't be ready until July of 2017.

That's 15 months later than planned.

Surprise! From $0.66 to $8.87 billion: original Plant Vogtle nuclear costs Who could have expected that, given that back in the 1970s and 1980s costs blew up 26 times the original estimate. Back then SO complained about paperwork after Three Mile Island. They're trying that same excuse now, but even a former Commissioner-turned-lobbyist is incredulous, as Kristi Swartz reported for the AJC yesterday, Monitor: Paperwork problems a drag on Vogtle schedule,

“It's taken eight months to handle paperwork deficiencies?” asked Bobby Baker, a former PSC commissioner who now represents Resource Supply Management, an energy consultant that works with large commercial, institutional and industrial electric customers.

A current Commissioner was almost as incredulous:

Continue reading