Tag Archives: William Jacobs

15 month delay for new Plant Vogtle nukes —state inspector at PSC

Southern Company's new nukes are delayed at least fifteen months, at least a billion over budget and rising, and not organized to meet safety filing requirements, yet the Georgia PSC yesterday let SO pass the buck to contractors and Georgia Power continue charging customers for that boondoggle, despite 40 to 1 opposition from attendees.

Ellen Reinhardt wrote for GPB News yesterday, Plant Vogtle Construction Costs Rising,

An independent auditor told utility regulators Plant Vogtle construction will be delayed at least 15 months and go millions of dollars over budget.

Nuclear engineer William Jacobs said poor construction material, contractor mistakes and oversight delays will mean the Unit 3 reactor won't be ready until July of 2017.

That's 15 months later than planned.

Surprise! From $0.66 to $8.87 billion: original Plant Vogtle nuclear costs Who could have expected that, given that back in the 1970s and 1980s costs blew up 26 times the original estimate. Back then SO complained about paperwork after Three Mile Island. They're trying that same excuse now, but even a former Commissioner-turned-lobbyist is incredulous, as Kristi Swartz reported for the AJC yesterday, Monitor: Paperwork problems a drag on Vogtle schedule,

“It's taken eight months to handle paperwork deficiencies?” asked Bobby Baker, a former PSC commissioner who now represents Resource Supply Management, an energy consultant that works with large commercial, institutional and industrial electric customers.

A current Commissioner was almost as incredulous:

Continue reading