Hatch 1 nuclear reactor down to 40% power Sunday: why?

Why is Plant Hatch Unit 1 running at well below capacity? Saturday 19 Jan 2013 that nuclear plant was at 100%, according to the NRC, yet Sunday it was down to 45%, then 40% Monday and 64% today. What's going on at Hatch 1? And what happened to nuclear supposedly being 24/7?

There's no event report about this from the NRC; the last item the NRC has on Hatch 1 seems to be from 2003. Southern Company provides no information on this event. Another source (Platts, 4 January 2013) says Hatch 2 (and Vogtle 2) are to refuel in the first half of this year, among Fifty-six US nuclear units to shut for refueling in 2013. But Hatch 1 is not on that list, and a similar Hatch 1 brownout happened 5 and 6 January:

Continue reading

Concrete flaws at Vogtle delay construction, require modified nuke permit

Concrete sinking into the dirt less than two months after licensing? One license amendment already requested and dozens more to come? Does this give you confidence in Southern Company's ability to build a safe nuclear plant without huge cost overruns charged to you the Georgia Power customer or you the taxpayer?

In mid-March the nuclear industry bragged about

Progress continues at the construction site of Plant Vogtle units 3 and 4 — the country's newest reactors and the first to be licensed since 1978.

We discover that at the end of March Southern Company had to ask NRC for a licensing change due to construction problems. Vogtle Nuclear Construction Faces “Additional Delay” Based on Miscalculations in Foundation Concrete — News Release from NC WARN and Alliance for Nuclear Accountability—April 9th, 2012, Continue reading