More cost overruns at Southern Company’s Kemper Coal in Mississippi

Why all these overruns?
All sorts of excuses about everything but
bad management and it was a bad idea in the first place.
Does anybody believe this coal plant will be completed anywhere near on time?
Why not stop wasting money on it and invest in solar and wind instead?



Only a few months after

the last cost overruns
,
Jeff Amy wrote for AP 2 July 2013,

Miss. Power: More overruns at Kemper power plant:
$4.45B price tag latest estimate
,

The unit of Atlanta-based Southern Co. told stockholders on Monday
that an ongoing review of costs at the coal-fired plant initially
has identified at least another $160 million in cost increases.

Mississippi Power spokeswoman Amoi Geter said Southern Co.
shareholders would absorb any cost increases. The parent company was
hit with $540 million in charges in April, although the after-tax
cost to shareholders was lower. In a January settlement with
Mississippi regulators, the company agreed to shield customers from
further cost increases.

The overruns could push the cost of the plant, adjoining lignite
mine and associated pipelines to $4.45 billion. That’s more than
$1.1 billion above original estimates.

It’s only supposed to produce 582 megawatts if ever completed.
SO could have already built far more solar and wind power
for that $4.45 billion, on time and on budget.

Why is

Plant Ratcliffe Kemper IGCC
so late and so expensive?

In a report to the Mississippi Public Service Commission,
Mississippi Power wrote that among the “cost pressures”
were problems with the productivity of construction labor, supplies
that the company is ordering to have on hand during the plant’s
start-up phase, and projected costs for fuel that the plant will
burn during start-up.



And they’re now up to two MS PSC members publicly criticizing
the plant.
Who knows? Mississippi’s PSC could grow a spine and cancel the thing.
Hm, and GA PSC could cancel Southern Company’s other
big boondoggle at Plant Vogtle.

Or we could peer into the future if this goes on.
Eileen O’Grady wrote for Reuters 1 July 2013,

Costs rise for Southern Co’s coal gasification plant
,

Duke Energy completed another IGCC plant last month in Indiana,
about one year late. The 618-MW Edwardsport plant, which was not
built to capture carbon emissions, cost $3.5 billion, up 75 percent
from early estimates.

So, who’s going to

downgrade
SO next?

-jsq