The WWTP is firing back up as we speak. —Tim Carroll

Tim Carroll’s response to
Gabe Fisher. -jsq

Gabe,

I know you are frustrated and pissed. My hope was with the info
below all could see the city has not just been idly sitting by. What
has been so frustrating for us is that our biggest problem is
outside of the city limits.

As discussed below, we are about 90% complete on the design for the
big force main project. Once completed it will eliminate the sewage
spills during high rain events in your neighborhood.



Just spoke with Larry Hanson and the WWTP is firing back up as we
speak. Soon you should start seeing the current spills end as the
system is brought fully back up and running.

Something I might add we could not have done so quickly had we not
taken the steps we did these past several days.

In regards to clean up —

Continue reading

What the sewer system is currently doing to our backyards —Gabe Fisher

Received today in response to

Tim Carroll’s email.



All, Gabe Fisher here—2420 Meadow Brook. I do not currently
have the time, nor mental capacity to fully think through this
issue, but I want you all to see what the sewer system is currently
doing to our backyards.

This video
was taken today, in by backyard,
after the flood. It has been spilling at least at this same rate for
the last 7 days.


What the sewer system is currently doing to our backyards —Gabe Fisher

Video by Gabe Fisher, Valdosta, Lowndes County, Georgia, 3 March 2013.

This contaminated water breached my crawlspace, around 24″ deep, and
must absolutely be dealt with ASAP. What is the city going to do for
me, and my neighbors who are in this same situation??

There is no other word for it—I am pissed. I have seen zero
results since the flood in 2009. Yes, maybe receiving 12″ inches of
rain is an act of God, but that does not account for all the man
made structures that force the flood waters higher at my location,
nor other obstacles it must overcome to quickly and efficiently
escape our area—such as the train trestle along Gornto. And it
absolutely does not account for the city’s poorly planned sewer
system..

This isn’t the first sewage spill since the flood of
2009—there have been countless others in my area. I have
photos and video evidence of at least 5 that would likely be
classified as ‘major’.

This cannot and will not be ‘swept under the rug’.. I am still
currently upside down on my property due to the flood of 2009 and
this current flood has only further degraded my property’s value.

Gabe

Looking at his address in the Lowndes County Tax Assessor’s maps,
and turning on Flood Map, Lakes and Rivers, and Aerial Photos,
you can see that his property and most of all his neighbors’
lots are in the flood plain:

Continue reading

The rest of the story on waste water —Tim Carroll

Received today from Valdosta City Council Tim Carroll, who
sent it to a long list of people,
apparently responding to
the VDT's recent article and editorials.

All,

During my tenure as a city councilman, I have tried to keep everyone
updated on events and issues with our city. I want to share and


email I sent out recently that hopefully you will agree is important
information. In regards to today's paper — the story has some
serious errors and omissions. First of all in 2009- all we saved
from the flood was the pump station. No sewage treatment was taking
place and contrary to what the VDT says, then as we are now —
raw sewage was going into the river. It lasted about a month in
2009. With the decision to pull equipment/tanks etc so they would
not be destroyed this year — we not only saved a lot of tax
payer money….but we will be able to bring the plant back on line
in about a week. Reducing by several weeks the amount of sewage
going into the river. In regards to city water systems being
compromised — considering our water plant is 10-15 miles north
of the WWTP and the amazing fact that the river flows south —
your water is completely safe. Do we like discharging raw sewage
into the river? Of course not. During the flood it was going to
happen either way.

I want to add one other note — the men and women in our
Utility department, fire, police, sanitation, engineering etc, etc

Floridan Aquifer

have been working long days this past week trying to manage flooding
issues. They deserve our thanks. It is very frustrating for those
whose homes and businesses were threatened by the flood. It is very
frustrating to our city employees who have worked so hard to manage
this crisis.

So as Paul Harvey says — “here is the rest of the
story”.

I think Council Carroll is a bit cavalier about
the city's wells being upstream of the wastewater treatment plant,
because while the river may flow south, it's not clear how
the Floridan Aquifer flows, especially with multiple 800 foot
deep wells sucking water out of it.
Also I wonder what people downstream of the Withlacoochee Wastewater
Treatment Plant think of all that raw sewage coming down at them,
especially considering some of them have wells downstream.

However, he makes a number of points that the VDT omitted,
including a plan to do something about the situation,
and appended is his "rest of the story".

Continue reading

VDT v Valdosta Re Wastewater

The VDT has apparently decided the City of Valdosta is to blame
for the
Withlacoochee Wastewater Woes,

and has made its case in a story and two editorials.
They seem to have forgotten about

the overflow in 2012
already.
And the VDT seems to have forgotten about it and its editor's own
apparent roles in the loss of the recent SPLOST election that
would have funded a new wastewater plant.

Jason Schaefer wrote for the VDT today,

Money saved at river's expense:
EPD investigates cause of sewage release as waters recede
,

When the flooding occurred in April 2009, the City made


extraordinary efforts to hold back the flooding, bringing in dirt
and heavy machinery to build a berm around the influent pump station
and other treatment equipment, working round the clock.

The efforts were successful. The treatment plant remained on during
the duration of the flood, and Valdosta's raw sewage remained
contained, though the facility incurred damages to its electrical
and biological purification systems, according to Utilities Director
Henry Hicks.

This year, the City opted for a different approach—cut
electricity to the underwater portions of the plant, submit to the
flooding and clean up afterwards.

The plant was “taken offline” Thursday at 9 a.m.
“to prevent further damage to equipment and associated
electrical and control systems,” according to a statement
issued by the Department of the City Manager.

The City stated that as a result of the shutdown, “untreated
sewage will be discharging directly into the river” at a rate
of between five and six million gallons of raw sewage per day.

In addition, the floodwaters were allowed into the plant and around
the remaining portions of the berm that was constructed in 2009
during the rising flood. Only half of the berm now remains, as the
other half was removed to allow access to the lower portions of the
plant, Hicks said.

So far, this year's response strategy seems to have saved the City
money. In 2009, about $500,000 was spent in manpower, equipment and
supplies to build the berm alone, and the plant, kept running,
incurred significant damages though raw sewage was kept out of the
river. This year, the money was not spent on the berm or to prevent
the flooding, and at least 15 to 20 million gallons of raw sewage
will have been released into the Withlacoochee by the time the plant
is back online.

There's more in the story, which is well worth a read.
Also note this inserted in the middle of the story:

Editor Kay Harris contributed to this story.

The VDT cites the EPA report,

National Enforcement Initiative (FY 2011 – 2013)
Keeping Raw Sewage and Contaminated Stormwater Out of Our Nation’s Waters
,
(more about that EPA initiative

here
)
and continues:

Continue reading

Videos of the Withlacoochee River in flood

Here are pictures and videos of the Withlacoochee River at GA 122

18 Feb 2013 Withlacoochee River @ GA 122


27 Feb 2013 Withlacoochee River @ GA 122

on

18 February 2013

(on the left when the river was rising)
and

27 February 2013
(on the right,
when it was clearly in flood stage).

Pictures and videos of the Withlacoochee River at GA 122
by John S. Quarterman and Gretchen Quarterman for

WWALS Watershed Coailition.




Brandon Powers for the VDT

And the Valdosta Daily Times has discovered video!
VDT posted 25 February 2013,

The effects of rain
,
which includes video of numerous locations around Lowndes County.
This is all relevant to the

Withlacoochee Wastewater Woes for Valdosta and Lowndes County.

-jsq

Withlacoochee Wastewater Woes for Valdosta and Lowndes County

AP picked up the story about flooding at Valdosta's Withlacoochee
wasterwater treatment plant, citing the VDT and the City
as sources.
The City of Valdosta thinks the County should contribute to replacing the plant,
or maybe the legislature will authorize a municipal option sales tax (MOST).

AP in GPBNews 1 March 2013,

Valdosta Treatment Plant Floods
,




Authorities shut down a Valdosta wastewater treatment plant as a river flooded critical buildings and structures. The city estimates an average of 5 million to 6 million gallons of untreated sewage will discharge daily into the Withlacoochee River until the flood waters recede and the plant can resume operation. (Photo Courtesy of John S. Quarterman via Flickr.)

VALDOSTA, Ga. —

Authorities shut down a south Georgia wastewater treatment plant as a
river flooded critical buildings and structures.

Valdosta city officials said power at the plant was shut down
Thursday to prevent further damage to equipment and control systems.

The city estimates an average of 5 million to 6 million gallons of
untreated sewage will discharge daily into the Withlacoochee River
until the flood waters recede and the plant can resume operation.

The AP story continues, but let's cut to the sources.

Continue reading

St. Augustine and Gornto Road in Final T-SPLOST list @ SGRC 2011-09-19

Maybe you’d like to know what are the T-SPLOST projects and how much they cost, so you can decide whether you think the tax is worth it (in addition to all the other considerations). That can take some work. Here’s an example.

Since Gretchen Quarterman asked what $5 million for one intersection would buy, T-SPLOST plans have been filed and a constrained list and then a final list approved by GDOT. Price tags jumped wildly up and down in the constrained list. For example, widening less than 3 miles of Old US 41 North from North Valdosta road to Union Road jumped from $8 million in June 2011 to $12 million in August.

In the final list, this item seems to be the one Gretchen was talking about:

RC11-000100 St Augustine Road at Gornto Road Intersection Improvements

You can find that one line on www.t-splost.com, which seems to be the state’s propaganda site for pushing T-SPLOST.

To find the current dollar amounts, you have to rummage around elsewhere until you find

Continue reading

You Build It, They Will Come: Quarterman Road Drag Strip



Carolyn Selby reminds the Lowndes County Commission at their regular meeting on 9 February 2010 that residents
asked the Commission to redesign Quarterman Road for slower traffic.

“You did throw us a bone by limiting the speed limit at 35 miles per hour.
But it’s not enforceable
We asked you to put in speed humps….
Nope. Couldn’t do that.

You designed a mile and a half straight-away, and they have come.
Welcome to the Quarterman Road Drag Strip!

She took pictures.
She called 911, and they caught one of the dragsters.
Neighborhood Watch in action.

The Commission responds by looking at County Engineer Mike Fletcher:

Continue reading