5.c. Cameron Lane widening for industrial park on US 84 W @ LCC 2012-07-23

While the Industrial Authority has been busily spiffing up its various Industrial Parks, everyone may have forgotten they have some competition west of town. Back in December 2010 Attorney Jack Langdale convinced the Commission in case REZ-2010-15 to rezone about 542 acres from R-1 to I-S, M-2, M-1, and P-D, which they did with fifteen conditions, which you can see in their minutes from 14 December 2010. As I recall it, one of the most convincing arguments was that the Langdales' own Kinderlou Subdivision is next door, so they wouldn't be doing anything to damage that, thus other neighbors could rest assured. Anyway, the next step was before the Commission at their Work Session this morning, for a vote tomorrow evening at their 5:30 PM Regular Session.

County Engineer Mike Fletcher presented agenda item 5.c., about Cameron Lane.

In December of 2010 the Board of Commissioners approved a rezoning case for the industrial park located off of highway 84, state route 38 west, near Wetherington Lane. The developers are beginning their master plan for the industrial park and will be utilitizng Cameron Lane as an entrance off of State Route 38 into the park. The developers are requesting to demolish Cameron Lane and rebuild a boulevard type entrance to serve the industrial park.

Attached are plats in front of you that show the existing and the proposed layout. The developer will be responsible for the acquisition of the the additional right of way that is required, as well as all engineering and construction costs for Cameron Lane. The new infrastructure will be built to county standards amd then will be brought back before the Commissioners for executive acceptance of infrastructure.

Commisioner Raines wanted to know if the county needed to deed the road over to the developer while all this was being done. Fletcher assured him the contractor would be responsible for everything.

Here's the video:

5.c. Cameron Lane widening for industrial park on US 84 W @ LCC 2012-07-23
Work Session, Lowndes County Commission (LCC),
Video by Gretchen Quarterman for Lowndes Area Knowledge Exchange (LAKE), Valdosta, Lowndes County, Georgia, 23 July 2012.

-jsq

This looks like gambling with my tax dollars. —Karen Noll

Received yesterday on “You can’t borrow yourself into prosperity.”:
The industrial authority’s spending of money seems to have no end. They don’t seem to budget appropriately or have a long range plan for the land they have acquired. Yet another industrial park when the Hahira park is still without any leasers.

This looks like gambling with my tax dollars. I don’t gamble with my own money for the reason that I am likely to loose. The board & staff feel no responsibility to the taxpayers. so, it is clear that they would ignore our demand for a no biomass clause and support of clean air for our families.

-Karen Noll