Before Lowndes County accepted stormwater, water, sewer, and road infrastructure for Camelot Crossing on June 23, 2026, here’s what the applicant provided as documentation and some of what county staff wrote about it. Or at least this is what the county returned in response to a LAKE open records request.
This material includes maps of all of the above infrastructure. But it does not say where stormwater is supposed to go when the detention pond fills up. Although there is a mysterious letter by an organization mentioned nowhere else, Valor Residential Group, promising pumps will be maintained by JWA and repaired or bypassed if they fail. Maybe that means like the pump that has been piping detention pond water into a sinkhole on the adjoining YMCA property?
There are several checklists from the county, one of which also has a version mostly checked off, but the others do not. Were all those items actually completed?
And there is a list from UES Professional Solutions 18, LLC to Hand Development, LLC, which lists fifteen (15) reports, many of which do not seem to be included in what the county sent.
Camelot Crossing Paperwork for Acceptance of Infrastructure @ LCC 2026-06-23
Stormwater
There’s a map of “Partial Storm Asbuilts” that seems to show all stormwater flowing into the detention pond in the middle of the subdivision. But it does not show any overflow. And I don’t know what it would overflow into, since there is no nearby creek. Continue reading
![[Collage @ LCC 25 March 2024]](http://www.l-a-k-e.org/govt/loco/2024-03-25--lcc-work-videos/many.jpg)
![[Packet: Solid Waste Franchises, Roads, Water Main, Hospital Revenue @ LCC 2024-03-25]](http://www.l-a-k-e.org/govt/loco/2024-03-25--lcc-packet/many.jpg)