According to an open records request of 17 February 2011,
the Industrial Authority says Wiregrass Power LLC still
“has not yet identified or completed a comprehensive list
of potential suppliers of raw materials,
goods and services required to construct and operate
the biomass electric generating plant.”
This is on a sheet entitled
“Owners/Investors/Suppliers/Contracts”, which also says:
“Site preparation and construction is not scheduled
to begin until June 1, 2011.”
Hm, what happened to breaking ground in January 2011?
The document also said a “Project Critical Path time-line is attached”
but it wasn’t.
Regarding buyers for the plant’s power: