Two more victories for anti-nuke activists:
San Onofre restart decision pushed back at least until June,
and webcasts of California Public Utilities Commission hearings going on right now.
Abby Sewell reported for the L.A. Times yesterday,
Decision on San Onofre pushed back to June at the earliest,
The plant’s operator Southern California Edison had hoped at one
point to have one of the plant’s two units operating by summer, but
NRC Chairwoman Allison Macfarlane made it clear that will not
happen.Macfarlane told reporters Tuesday after a speech, “You know, the
process is very complicated now. Almost every day it gets a little
more complicated…. Right now I can tell you a decision on restart
won’t happen until the end of June, certainly after the middle of
June.“It may get pushed back later,” she said. “I don’t know.”
She didn’t say much about the Atomic Safety and Licensing Board (ASLB)
decision to require NRC public hearings before any decision on
restarting San Onofre,
but she did say this: