According to Power-Gen Worldwide,
Plans for biomass power plant ends:
The company still has a permit to build a 55 MW plant in Florida but
there are no plans to start construction and the company is expected to
let the permit lapse in June. Adage ended plans in 2010 to build another
plant in Florida.
Why is Adage giving up on Hamilton County, Florida?
Christopher Dunagan writes in Kitsap Sun:
Meanwhile, a similar project by Adage in Northern Florida also will not
be pursued at this time, according to DePonty. That project has been
fully permitted and was about to move ahead if only the electricity
market had provided the financial incentive, he said.
Here’s the
Florida air permit.
Despite having that air permit and promising
jobs, jobs, jobs
Adage is apparently not going to build in Hamilton, County, Florida.
The source of the many stories on this appears to be